Epic Software index login search
spacer
 
Blog Archive
2016
June (1 )
2013
December (1 )
August (2 )
July (1 )
March (1 )
February (3 )
2012
December (1 )
November (1 )
August (2 )
July (1 )
June (3 )
May (1 )
April (2 )
March (3 )
February (2 )
January (6 )
2011
December (4 )
November (4 )
October (6 )
September (6 )
August (6 )
July (4 )
June (4 )
May (7 )
April (6 )
March (4 )
February (4 )
January (5 )
2010
December (6 )
November (3 )
October (3 )
September (1 )
August (3 )


By Bloger
Vic (30 )
Anthony (2 )
Andrew (3 )
Adam (2 )

Back to the Blog

Our Blog

RSS Feed for this Blog

   
title_blog.jpg

AC Units Installed - Kitchen Cabinets Installed - Wallboard and Electrical Work Continue

May 15, 2011 - The big news this week was the installation of the two, 5 ton AC units on the roof of the building, and getting started on the kitchen in the Silver Rock unit. We also got all of the wallboard installed (except for the ceiling in the video production room), and second layer of mud on the walls that were taped and floated last week. We picked up a load of steel for the ADA ramp and got a close out inventory of Italian ceramic tile delivered to the epic Creative Co-Op at a great price.

Fernando Sanchez of Flex Builders came by with two 13 SEER AC units that will cool the Silver Rock units and the big video production room. During the design phase of the project he suggested we place the units on the roof for security and aesthetic reasons. We used Mike's bucket truck (Gulf Coast Graphics) which quickly lifted the units to the roof. Each unit was positioned on the platform we built and bolted down several weeks ago. We also did some things to insure the AC units will provide years of uninterrupted service.

Rectorseal company makes a product called Kickstart® which is designed to help hard start AC compressors. Starting up a big unit is rough on it, and a Kickstart cacacitor will extend the life of compressors they are used on. They work by bringing up the AC compressor to full speed more quickly and efficiently. They also assist compressors in starting under very adverse ambient conditions such as low voltage or high head pressures. Our AC units comes with a 10 year parts and labor warranty, and this should further extend the life of the equipment.

Fernando hooked up the electrical power to the units and then charged the system. He then turned on the units and wonderful cool air came out the vents. After we get the ceiling and doors in place on the interior, he will return to balance the system and insure even distribution of the airflow. At this time we only installed 2 of the 4 units needed for the entire building. Cash flow is becomming a problem, so the units that have not yet been rented do not have the HVAC system installed. Once we have tenants for these lofts, Fernando will return and complete the installation process.

Lalo was able to get the electrical wiring done in units 9 & 10.  He also did all the pre-wiring for the exit signs needed.  We ordered 8 battery back up exit signs from ebay, and they should be in this week. These are the "frog eyes" types of lights you see in many commercial buildings, and we ordered them in black to match the walls. We made the required changes that the Centerpoint electrician required, so we put in a call to them to come out and hook up the permanent electric service to the building.  While they are here, they will straighten the utility pole that is leaning not by using a guy wire, but injecting foam into the ground. I am looking forward to seeing how they do it.

We completed installing most of the remaining wallboard, and added a second layer of mud to most of the joints. We purchased a texture gun from Harbor Freight ($20) and a bag of texture ($12) and did some tests which turned out really nice.  Once the taping and floating is done, we will texture all the walls.  We still have the ceiling in the big room to do, and I am debating if we should tackle this ourselves, or get a wallboard company to do it.

Late in the week, we turned our attention to the kitchen, and began working with the Aluminum Composite Material (ACM) from Diassa and ALPOLIC. This material is wonderful to work with if you have the right tools, and we do thanks to Chris Larimore of Diassa. Chris has let us borrow his wall saw, and a special router tip he developed for working with the ACM.  We are using it in the kitchen for the walls and some of the under counter surfaces. It looks beautiful. We installed some of the cabinets that were donated to the project by James Larimore, and built a cabinet for the microwave/oven wall unit using the ACM panels.

For the first time in over 90 days, we got rain this week, and it flash rusted the metal handrails we had put in the week before.  We removed the rust and added a coat of metal primer followed by a industrial grade oil based paint. We also started to paint the trim around the windows which will be a time consuming task, but really looks good.

Next week we will focus on getting the ceiling up in the big room, so we can get the attic insulated. We will start texturing and doing the trim details. We have 5-6 small loads of dirt scheduled for delivery that will be used to level off some of the low spots around the building, and get it ready for the flat-work concrete walk and boarder around the building. 




Posted by on May 15, 2011


Send this article to your friends
Facebook Email Digg Designfloat del.icio.us Ask Google Twitter Amazon Wishlist Nujij BuddyMarks Squidoo MySpace Multiply LinkedIn oneview Bebo

Post A link on your blog or webpage!

Post URL on your blog or webpage!

E-Mail As A link Mailto
Add to your Favorites
More Shareing Options

Comments


No Comments made yet


Leave a comment

Name:
Email:
Your Comment
Notify me of follow-up comments?
 



The two, 5 ton AC units arrive and are removed from their boxes.

Fernando, Mike and Adam rig up the first unit to the bucket truck.

The first AC unit is carefully hoisted into place by Adam.

The unit reaches the top of the roof and is positioned into place.

The AC unit is placed on top of the platform we built and installed several weeks earlier.

We added a Rectorseal Kick Start unit that will help increase the life of the compressor.

A metal roof jack was used to bring the copper tubing into the building and keep the transition water tight.

The copper pipes were hooked into the air return units in the attic.

the rough electrical work was completed in units 9 and 10.

The wallboard in units 9 & 10 were completed.

Taping and floating the wallboard.

Metal edging on all the corners of the wallboard were finished this week as well.

Window sills were cut to size for all windows. They will be installed after the walls are textured.

A door was added to the 2nd floor utility room.

This room will be used for storage and for the AC ducting to the 2 lofts for lease.

We did some testing using a $20 texture gun and it worked well.

Almost all of the wallboard was completed in the big room. The ceiling remains.

We bought a closeout inventory of Italian tile.

The oven, cabinets and Aluminum Composite Material (ACM) were installed in the kitchen.

We started painting the window trim, and painted the handrails for the ADA ramp.

 
 